Aggregate & Stone / Limestone

How Much Limestone for a 10×20 Driveway?

A 10 × 20 ft driveway (200 ft²) at 4″ deep needs 3.9 tons of crushed limestone — 2.47 yd³ net plus 10% waste. Order 4.00 t — quarries sell by the ton; a tri-axle carries about 20 tons per load.

10×20 at other depths

DepthVolumeOrder (tons)50 lb bag (0.5 ft³)
2″ 1.23 yd³ 2.0 tons 74
4″ (this page) 2.47 yd³ 3.9 tons 147
6″ 3.70 yd³ 5.9 tons 220

Other driveway sizes

2″ top course · 4″ base · 6″ driveway base
Compaction + waste
Material orderLIMESTONE · 10×20 ft × 4″
3.9tons

Order 4.00 t — quarries sell by the ton; a tri-axle carries about 20 tons per load.

Area
200 ft²
Volume (66.7 ft³)
2.47 yd³
Net weight @ 1.45 t/yd³
7,160 lb · 3.58 t
Waste / settling 10%
+ 0.36 t
Order quantity
3.94 tons
Truckloads
1 × tri-axle dump (≈20 t)
Metric
1.89 m³ · 3.57 tonnes
Bagged instead
50 lb bag (0.5 ft³)
147 bags
Est. delivered
Materials + delivery$25–$55 / ton · Sep 2026
$185 – $305
Installed (with labor)typ. $335
$244 – $463
Shop this ticketThe Home Depot

Quantities follow the ticket. Links may earn us a commission at no cost to you; they never change a number.

What will this limestone job cost?

See the installed price range for these quantities and get up to 3 quotes from local contractors. Free, no obligation.

Cost + local quotes →

Different size or depth?

Open the full limestone calculator to change every input, pick a material and see truckloads.

Limestone calculator →

How to calculate crushed limestone by hand

Tons = Length (ft) × Width (ft) × Depth (in) ÷ 12 ÷ 27 × 1.45 t/yd³

Worked example

  1. Area: 50 ft × 12 ft = 600 ft².
  2. Volume: 600 ft² × (4 in ÷ 12) = 200 ft³ = 7.41 yd³.
  3. Weight: 7.41 yd³ × 1.45 t/yd³ = 10.7 tons.
  4. Compaction and waste 10%: 10.7 × 1.10 = 11.8 tons → order 12 tons, one tri-axle load.
Field reference
1 ton #57 limestone at 4″
≈ 56 ft²
1 ton #57 limestone at 2″
≈ 112 ft²
1 yd³ crushed limestone
≈ 2,900 lb · 1.45 t
Tri-axle dump
≈ 20 tons

Questions crews ask

How much limestone do I need for a driveway?

Square feet × depth in inches ÷ 324 gives cubic yards; × 1.45 gives tons. A 12 × 50 ft driveway at 4″ of #57 is 7.4 yd³ ≈ 10.7 tons; order 12 with compaction. For a new driveway lay 4–6″ of ¾″ minus first, then 2″ of #57.

How much does a ton of limestone cover?

About 56 ft² at 4″ deep, 75 ft² at 3″ and 112 ft² at 2″ for #57. Limestone is a little denser than granite gravel, so a ton covers slightly less than the 1.4 t/yd³ figures used for generic gravel.

What is #57 limestone used for?

#57 is ¾″ washed stone with no fines: driveway top course, drainage around pipes and foundations, under slabs and in French drains. It stays loose and drains. For a base that locks together use ¾″ minus or screenings.