Concrete & Masonry / Concrete

Concrete Calculator

Yield in cubic yards, bag counts for 80 / 60 / 40 lb, the ready-mix ticket in ¼-yard steps, and which one to buy. Waste covers sub-grade irregularity and spill — 10% is normal for a slab on grade. Results update as you type.

4″ patio / walk · 5–6″ driveway · 6″+ garage
Waste
Order · incl. wasteCONCRETE · slab
4.62yd³

Order 4.75 yd³ ready-mix — plants ticket in ¼-yd³ and most charge a short-load fee under ~5 yd³.

Net volume (113.3 ft³)
4.20 yd³
Waste 10%
+ 0.42 yd³
Ready-mix ticket
4.75 yd³
Approx. weight
17,000 lb
What to buy
80 lb bags
208
60 lb bags
278
40 lb bags
416
Est. delivered
Materials + delivery$125–$180 / yd³ · Sep 2026
$694 – $955
Installed (with labor)typ. $2,513
$1,714 – $3,675
Shop this ticketThe Home Depot

Quantities follow the ticket. Links may earn us a commission at no cost to you; they never change a number.

What will this concrete job cost?

See the installed price range for these quantities and get up to 3 quotes from local contractors. Free, no obligation. Also: Driveway cost.

Cost + local quotes →

Common slab sizes, answered

How to calculate concrete by hand

Cubic yards = Length (ft) × Width (ft) × Thickness (in) ÷ 12 ÷ 27 · 80 lb bags = ft³ ÷ 0.60

Worked example

  1. Area: 20 ft × 17 ft = 340 ft².
  2. Volume: 340 ft² × (4 in ÷ 12) = 113.3 ft³ = 4.20 yd³.
  3. Waste 10%: 113.3 × 1.10 = 124.7 ft³ = 4.62 yd³ → ready-mix ticket 4.75 yd³.
  4. Bags instead: 124.7 ÷ 0.60 = 208 × 80 lb bags (or 277 × 60 lb, 416 × 40 lb).
  5. Above 1 yd³, ready-mix costs less than bags even with a short-load fee — order the truck.
Field reference
1 yd³ of concrete
45 × 80 lb · 60 × 60 lb · 90 × 40 lb bags
1 yd³ at 4″ thick
≈ 81 ft²
1 yd³ at 6″ thick
≈ 54 ft²
80 lb bag yield
0.60 ft³ · ≈ 1.8 ft² at 4″

Questions crews ask

How many bags of concrete do I need?

Multiply length × width × thickness (in feet) for cubic feet, add 10% waste, then divide by the bag yield: 0.60 ft³ per 80 lb bag, 0.45 per 60 lb, 0.30 per 40 lb. A 10 × 10 ft slab at 4″ is 33.3 ft³ → 36.7 with waste → 62 × 80 lb bags.

How many 80 lb bags of concrete make a yard?

Exactly 45: a cubic yard is 27 ft³ and an 80 lb bag yields 0.60 ft³. It takes 60 × 60 lb bags or 90 × 40 lb bags. At $6–$7 a bag that is $270–$315 per yard in bags versus $125–$180 for ready-mix, which is why trucks win above a yard.

How much does a yard of concrete cover?

81 ft² at 4 inches thick, 65 ft² at 5″, 54 ft² at 6″. Divide 324 by the thickness in inches to get square feet per cubic yard.

Should I use bags or order ready-mix?

Bags below about 1 cubic yard (45 × 80 lb bags — a lot of mixing). Ready-mix above that: plants ticket in ¼-yard steps and most charge a short-load fee of $75–$150 under 4–5 yards, but you still come out ahead and the pour is done in an hour.

How thick should a concrete slab be?

4″ for patios, walkways and shed floors; 5–6″ for driveways and garage floors; 6″ or more with rebar for anything that carries trucks or heavy equipment. Always over 4″ of compacted stone base.

How much waste should I add to a concrete order?

10% for a slab on grade — sub-grade is never perfectly flat and the truck never gives you the last bit. 5% for a formed footing, 15% for a rough or hand-dug excavation. Running short mid-pour costs far more than the extra quarter yard.